Board Presents 2021-2022 Community Planning and Partnership Update

At last night’s Regular Board Meeting, Trustees received an update on the Long Term Capital Plan, which includes planning for future Board initiatives. 

All school boards in Ontario are required to share with community partners information regarding their long-term capital plans.  St. Clair Catholic’s Long Term Capital Plan provides background information with respect to the Board’s future capital needs and accommodation strategy and a framework for decision-making regarding facilities.  The report provides specific data and information related to enrolment trends, facility conditions and strategies and schedules for accommodation.

“Our annual report to Trustees and our community partners shares important planning information,” says Amy Janssens, Associate Director – Corporate Services & Treasurer.  “Projects named in the report have all been identified by the Board as priorities; however, they are all at various stages of Ministry approval.”

The report is an update to the 2018-2022 document.  A new Long Term Capital Plan is scheduled to be released in September 2023.

Highlights for the 2021-2022 Budget Year:

E1: Sarnia

  • Complete design and begin construction of Sacred Heart Replacement School
  • Procure additional portables for Gregory A. Hogan and St. Anne, Sarnia if required

 E2: Lambton County                           

  • Procure additional portables for St. Joseph, Corunna and St. Philip, if required
  • Begin design of child care addition and renovation at St. Joseph, Corunna
  • Begin design of child care expansion and school addition at St. Philip

 E3: Wallaceburg                      

  • Complete design and begin construction of portapak replacement at Sacred Heart, Port Lambton
  • Begin design of portapak replacement at Christ the King
  • Procure portables for Christ the King, if required

 E4: Chatham                                        

  • Complete purchase of land for South Chatham Elementary School
  • Complete design and begin construction of South Chatham Elementary School
  • Open newly retrofitted Monsignor Uyen in former Our Lady of Fatima school building
  • Sell St. Vincent and Monsignor Uyen

 E5: Kent County                                   

  • Procure portables at St. Anne, Blenheim, if required

 S2: Kent County – UCC                       

  • Submit land priorities application to purchase land for Ursuline College Replacement School
  • Begin design of Ursuline College Replacement School

 Highlights for the 2022-2023 Budget Year:

E1: Sarnia                                             

  • Complete construction of Sacred Heart Replacement School
  • Procure additional portables for Gregory A. Hogan and St. Anne, Sarnia if required
  • Declare Sacred Heart Sarnia surplus and initiate disposition process (Ontario Regulation 444/98)

 E2: Lambton County                          

  • Procure additional portables for St. Joseph, Corunna and St. Philip, if required
  • Complete design and begin construction of child care addition and renovation at St. Joseph, Corunna
  • Complete design and begin construction of child care expansion and school addition at St. Philip

 E3: Wallaceburg                                 

  • Complete construction of portapak replacement at Sacred Heart, Port Lambton
  • Complete design and begin construction of portapak replacement at Christ the King
  • Procure portables for Christ the King, if required
  • Investigate accommodation review for Wallaceburg planning area

 E4: Chatham                                        

  • Complete construction of South Chatham Elementary School
  • Declare Georges P. Vanier and St. Ursula surplus and initiate disposition process (Ontario Regulation 444/98)

E5: Kent County                                    

  • Procure portables at St. Anne, Blenheim, if required

 S2: Kent County – UCC                       

  • Complete design and begin construction of Ursuline College Replacement School